§ 59-31. General procedure.  


Latest version.
  • The procedure by which a developer gains approval for a subdivision is described in this article. The procedure is mindful of the interests of the subdivider, the potential buyer of the subdivided land, and the surrounding community. The procedure is in four steps and consists of:

    (1)

    Informal presentation of a sketch plan for discussion (optional);

    (2)

    Formal submission of a preliminary plan for approval;

    (3)

    Formal submission of a final plat for approval; and

    (4)

    Recording of a final plat.

    Step 2 shall be completed prior to making improvements associated with subdivision development. Steps 3 and 4 shall be completed prior to the sale of any lot within the proposed subdivision.

(Ord. No. 99-4-20, § 1(art. VI(A)), 4-26-1999)